Payment for work without a written contract

A contract may be unenforceable while a separate payment claim remains open.

In Pavey & Matthews Pty Ltd v Paul [1987] HCA 5; (1987) 162 CLR 221, the High Court of Australia considered that distinction in a NSW building dispute. Its decision let a builder pursue reasonable payment for completed work. It did not decide how much more, if anything, the owner owed.

The work was agreed by word of mouth

A licensed builder renovated Mrs Paul’s cottage. She had agreed to pay a reasonable amount based on prevailing building industry rates. There was no written contract.

Mrs Paul paid $36,000. The builder claimed another $26,945.50. She disputed whether the charges were reasonable and relied on section 45 of the Builders Licensing Act 1971 (NSW). That provision made the building contract unenforceable against her unless it met the written-contract requirements (Mason and Wilson JJ, [1]-[4]; Deane J, [1]-[3]).

The claim had a different legal basis

By four judges to one, the High Court held that section 45 did not bar the builder’s claim for reasonable payment, known as a quantum meruit.

Mason, Wilson and Deane JJ treated the claim as restitution: an obligation imposed by law for work requested and accepted, rather than enforcement of the oral contract. Dawson J agreed with the result on a different legal basis. Brennan J dissented.

The Court restored the earlier ruling on this preliminary issue. The remaining issues, including the reasonable amount payable, still had to be resolved (Mason and Wilson JJ, [10]-[17]; Deane J, [13]-[25]; Dawson J, [14]-[15]; Brennan J, [21]-[23]; Court’s orders).

The limits matter

This was a decision about a particular NSW provision in 1987. It is not a rule that all work must be paid for despite a failure to meet legal requirements. In a later case, the High Court explained that Pavey & Matthews did not establish that accepting a benefit alone was enough to support a payment claim (Lumbers v W Cook Builders Pty Ltd (in liquidation) [2008] HCA 27, [83]-[86] (Gummow, Hayne, Crennan and Kiefel JJ)).

Nor does “unjust enrichment” let a court award money simply because that seems fair. The claim must satisfy the relevant legal rules (Redland City Council v Kozik [2024] HCA 7, [179]-[180] (Gordon, Edelman and Steward JJ)).

Questions for your lawyer

  • If the contract cannot be enforced, is there a separate legal basis for payment?

  • What evidence shows which work was requested, accepted and reasonably worth paying for?

  • Do the laws applying to this work restrict the claim?

Nicky Wang, Principal Solicitor

Nicky Wang is Principal Solicitor of Clean Law, a Sydney-based legal practice focused on civil litigation cost behaviour, settlement structure, litigation funding control, and client-side cost visibility. Her work examines how legal costs, incentives, information timing and role design affect the real financial outcome of civil disputes.

Previous
Previous

Claiming for a building delay? Show what it held up