Missed a delay notice: can a builder still get more time?

Case: Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd [2002] NSWCA 211

Sometimes. In Peninsula Balmain Pty Ltd v Abigroup Contractors Pty Ltd [2002] NSWCA 211, a separate power to extend time remained available despite the builder’s failure to follow the claim procedure. The result depended on the contract’s wording: [69]-[81].

A missed notice and a power to extend time are different questions.

The dispute

Peninsula engaged Abigroup for a residential development in Balmain. Their contract used AS2124-1992 conditions with changes. Peninsula later terminated the contract and claimed damages for late completion: [4], [6], [19], [23].

Abigroup had not followed the procedure for claiming the further extensions of time in dispute. A court-appointed referee nevertheless found that the completion date should be extended. Peninsula challenged that finding: [69]-[76].

What the contract allowed

Clause 35.5 required a written claim within 28 days after the delay occurred. But it also let the superintendent extend time before the final certificate, even where the builder had no entitlement to an extension: [9].

The Court held that this separate power could serve both parties. The superintendent had to decide honestly and impartially whether to use it. The power did not automatically end when the contract was terminated for the builder’s breach: [79]-[80].

On these facts, the referee could decide what the superintendent should have done and allow the justified extensions. That reduced the period for which late-completion damages were payable. Peninsula still succeeded in the appeal on other issues: [69], [81], [108].

Why the wording matters

This was no general excuse for missing a deadline. The Court said that delay in making a claim could justify refusal if it made the claim difficult to assess: [79].

Later cases show the limit. In Growthbuilt [2021] NSWSC 290, different wording expressly removed any obligation to extend time or consider doing so. The Court distinguished Peninsula Balmain: [69]-[80]. In Tallai [2026] NSWSC 1332, a power exercisable solely for the contractor’s benefit also led to a different result: [83]-[90]. NSW Caselaw

Questions for your lawyer

  • What notices does our contract require, by when and to whom?

  • Is there a separate power to extend time, and what limits apply?

  • What records show the cause and length of each delay?

Nicky Wang, Principal Solicitor

Nicky Wang is Principal Solicitor of Clean Law, a Sydney-based legal practice focused on civil litigation cost behaviour, settlement structure, litigation funding control, and client-side cost visibility. Her work examines how legal costs, incentives, information timing and role design affect the real financial outcome of civil disputes.