Burger King v Hungry Jack’s: when approval powers block performance

Home > Case Law Library > Contract > Burger King Corporation v Hungry Jack’s Pty Ltd [2001] NSWCA 187 (NSW Court of Appeal | 21 June 2001)

Published: 30 January 2025 | Reviewed: 8 October 2026
(3-minute read)

A business may promise to meet a target but need the other party’s approval to do so. What happens if that approval is withheld to stop it meeting the target?

That problem arose in Burger King Corporation v Hungry Jack’s Pty Ltd [2001] NSWCA 187.

Growth depended on approval

Hungry Jack’s agreed to open at least four new restaurants each year across Western Australia, South Australia and Queensland. New restaurants required Burger King’s approval, including financial and operational approval. [49]-[65], [89]-[95]

Burger King froze the recruitment of third-party franchisees and withheld approvals. It later sought to end the development agreement because Hungry Jack’s had not opened enough restaurants. [188]-[191]

“Sole discretion” had limits

The Court held that the agreement contained implied duties of good faith and reasonableness. Without those limits, Burger King’s broad approval powers could undermine the development rights the agreement gave Hungry Jack’s. [176]-[186]

Burger King could protect its own legitimate interests. It did not have to put Hungry Jack’s interests first. But it could not use its approval powers for a purpose foreign to the contract, such as blocking development to create a basis for ending the agreement. [185]-[187]

The Court upheld findings that the franchisee freeze and the withholding of approvals breached those duties.

The termination clause was not the whole answer

There was a separate reason the notice based on the restaurant target failed.

Reading the agreement as a whole, the Court held that Hungry Jack’s had a further 12 months to make up the shortfall before that failure could justify termination under the relevant clause. Burger King’s notice did not allow for that period. [95]-[111]

The appeal did change parts of the damages award. Both the appeal and Hungry Jack’s cross-appeal succeeded in part. The Court directed that damages be recalculated. [759]-[763]

What this means for your contract

Read a performance target alongside the powers that control whether it can be met.

Before signing, consider whether the contract needs clear approval criteria, response times and a process for delay. If a dispute arises, keep the requests, replies and reasons for refusal. These are practical steps drawn from the case, rather than rules the Court prescribed.

The decision concerned a particular agreement and particular conduct. It does not establish that every refusal of approval is unlawful or that every commercial contract contains the same implied duties.

Questions to ask your lawyer

  • Which duties depend on the other party’s approval or co-operation?

  • What limits apply to its power to refuse or delay?

  • Must extra time or a chance to fix the problem be given before termination?

By Nicky Wang
Principal Solicitor
Nicky Wang, Principal Solicitor

Nicky Wang is Principal Solicitor of Clean Law, a Sydney-based legal practice focused on civil litigation cost behaviour, settlement structure, litigation funding control, and client-side cost visibility. Her work examines how legal costs, incentives, information timing and role design affect the real financial outcome of civil disputes.

Previous
Previous

Can an arbitration clause cover a challenge to the deed itself?

Next
Next

Good faith negotiations: must you reach a deal?